Case Study from | S-5!

The Project

Parallel Products is a leader in the sustainability industry, the ethanol industry and in green energy production—a one-stop sustainability shop. Many of its clients are subject to zero-landfill policies, so Parallel Products repurposes and recycles common materials.

Located in historic New Bedford, an old whaling town on the Southern Coast of Massachusetts, Parallel Products of New England (PPNE) recently completed its Duchaine Boulevard project, a center for processing and technology development—on its 130-acre campus for recycling and the production of green energy.

The campus houses solar energy, green energy production and recycling recovery. The solar energy generated on-site reduces energy costs and fossil fuel consumption for energy, ultimately resulting in decreasing the company’s carbon footprint and contributing power back to the grid.

The new Duchaine Boulevard facility features a standing seam metal roof with 1.9 MW of rooftop solar PV. The EPC contractor recommended the S-5! PVKIT® — a direct-attach rail-less solar solution to provide a secure, economical and penetration-free method for attaching the solar modules to the metal roof.

 

The Challenge

PPNE processes/recycles glass, aluminum and recyclable plastic containers collected through Massachusetts’s bottle deposit program. PPNE had identified a need for a glass processing facility as the state’s only bottle production facility closed in 2018, leaving the Commonwealth with limited solutions for glass handling and a large accumulation of glass due to difficulties in transporting glass to out-of-state recycling markets.

The new glass processing Duchaine Boulevard facility is a necessary development for the Commonwealth to ensure the recycling of glass bottles versus disposal and/or lower value usages such as fill.

The company’s main goal was to offset its carbon footprint since PPNE annually processes 3,710 tons of aluminum, 3,892 tons of recyclable plastic containers and now 50,000 tons of glass, utilizing heavy machinery and equipment that consume an enormous amount of power.

 

The Solution

PPNE decided the best way for it to offset its electrical usage was to add solar. This new facility has increased solar capacity by 1.9 MW, part of its greater 4 MW solar initiative on campus. 

PPNE chose the PVKIT and S-5-V Mini clamps to secure the solar panels to the metal roof.  The PVKIT’s pre-assembled components enabled solar installers to “lay & play” PV modules with tested, engineered, cost-saving, attachment.

The project has enabled PPNE to further its sustainability goals. Not only is the company offsetting its carbon footprint, but it has also far exceeded what it consumes on-site and is selling power back to the grid via the local utility company through the Solar Massachusetts Renewable Target (SMART) Program, a long-term sustainable solar incentive program that promotes cost-effective solar development in the Commonwealth of Massachusetts.

 

Long-Term Outlook

Once a Polaroid manufacturing facility (now dubbed the green energy center), PPNE recycled and repurposed a rather neglected and underutilized property, and with the addition of rooftop solar, is now generating power, providing recycling services, adding jobs locally and contributing to the economic development of the city.

“The S-5! PVKITs and S-5-V Mini clamps really work well on the type of buildings we generally use in the recycling business, which are prefab standing seam metal roofs. The installation was much faster than we anticipated. With on-site demonstrations and installation instructions provided by S-5!, there was a really short learning curve and a really clean installation. If you take a bird’s eye view, the system is clean and attractive; it almost looks like an extension of the building. S-5! direct-attach looks natural, non-obtrusive, built-in, sleek and low-profile. S-5! is a great product, and I would highly recommend it.”―Tim Cusson, VP of Business Development, Parallel Products, New Bedford, Massachusetts

 

Project Team

Owner Developer: Parallel Products

EPC: ECS Electric, Inc.

Module Manufacturer: CSUN

Inverter Manufacturer: Solectria

Mounting/Racking Manufacturer: S-5!

 

Project Stats:

  • Roof Profile: 3” trapezoidal double-lock standing seam metal roof
  • Roof Measurements: Total >150,000 square feet
  • Roof Pitch Varies: ½:12 to 3:12
  • Project Size: 1.9 Megawatt
  • S-5! Products Supplied:
  • PVKIT® (6500)
  • S-5-V™ Mini clamp (6500)

 

The content & opinions in this article are the author’s and do not necessarily represent the views of AltEnergyMag
S-5!

S-5!

In 1992, S-5! invented the very market space of manufactured roof attachment solutions. S-5!'s clamps and brackets are engineered for a variety of applications, including residential and commercial solar installations on exposed-fastened and standing seam metal roofing. The company has a portfolio of more than 5+ GigaWatts of rooftop solar arrays, including many Fed-Ex and Walmart buildings; 700 Costco stores in eight countries; international airports; and corporate headquarters for Google, IBM, NATO, NREL and Apple. S-5! technologies are also affordable for domestic applications with more than 15,000 such solar installations in 50 countries.

Other Articles

Demolition Ranch HQ, Boerne, Texas―Case Study
Due to the ranch’s remote location, the owner wished to build an off-the-grid building featuring a 3.84kW rooftop solar array together with a battery storage system to power the building. The rooftop solar modules are secured in place using the ProteaBracketTM by S-5!
Simplifying Solar Module Installation
The MLPE mount provides flexibility to install the MLPE device on the underside of the module frame at desired locations so wire management is simplified. The tab feature eliminates hassle
Wire Management of Rail-Less Solar PV Systems on Low-Slope Metal Roofing
Module Preparation & Strategic String Design - Part I. By strategically designing module and string layouts, prepping modules in staging areas and performing repeatable installation procedures, all hurdles to installing rail-less solar can be overcome.
More about S-5!

Comments (0)

This post does not have any comments. Be the first to leave a comment below.


Post A Comment

You must be logged in before you can post a comment. Login now.

Featured Product

Raptor Maps - The integrated operating system for end-to-end solar management

Raptor Maps - The integrated operating system for end-to-end solar management

Operate autonomous drones and other robotics technology on your solar farms with Raptor Maps' robotics operations platform. Our end-to-end solution allows you to build and schedule data collection missions, to analyze collected data through our analytics engine, and to address identified issues through our remediation intelligence suite. From construction monitoring to substation inspections to SCADA-alert generation missions, Raptor Robotics gives your team unparalleled insights into the health and status of your project. Improve the safety, efficiency, and scale of your operations with Raptor Robotics.