The Coming Storage Boom: Project Proposals Nearly Double California's Storage Target

California’s push to transform the market for grid-scale energy storage is working even better than expected -- at least on paper.
 
Last year, California created a mandate calling for 1,325 megawatts of energy storage projects by 2020, to be scaled up every two years. The first installment of proposals due this year adds up to 200 megawatts.
 
As of mid-2014, more than 2,000 megawatts of energy storage projects have applied to interconnect with the state’s grid, according to recent data from state grid operator California ISO (PDF). In other words, project developers have received the market signal of a 1.3-gigawatt mandate and proposed enough storage to provide nearly double that amount over the coming years.
 
The list includes 1,669 megawatts of standalone battery storage, 44 megawatts of other standalone storage, 255 megawatts of batteries combined with generation projects, and a 90-megawatt project combining solar and batteries. They are all seeking interconnection under the initiative's “Cluster 7” window, which closed on April 30, 2014. (A project-by-project breakdown of all the applications is available in PDF.)

Comments (0)

This post does not have any comments. Be the first to leave a comment below.


Post A Comment

You must be logged in before you can post a comment. Login now.

Featured Product

Nature’s Generator MyGrid 10K

Nature's Generator MyGrid 10K

A 10,000W plug & play whole-home generator with a 10kWh LiFePO4 battery for reliable backup power. Features easy setup, flexible 120V/208-240V input, and solar/wind charging. Expandable with extra batteries or solar panels, and can pair two units for 20,000W for even larger energy needs. Powers your home during power outages, reduces electricity costs, and supports sustainable energy.